For the nautical set not familiar with boating on New York waters – the East River is as bustling as Times Square – but exhibiting traits consistent with that of a tidal strait, it’s not always in a nice and welcoming way.
Lamentably, the marina’s initial protective shield was only deflecting a portion of wave energy back into the river and failed to reduce the tidal impact hammering through the aperture under the piers. A restructuring with extensive sustainable design elements was in order to prevent further irremediable damage.
One° 15 Brooklyn Marina, tide and traffic troubles
But the tides don’t tell the One° 15 Brooklyn Marina whole story. The river is a melting pot of moving crafts cutting their own courses with distinct “coming and going turning points.” For example, the daily cavalcade consists of: commercial freighters and tug boats; Jet-skiers chasing the transom chop from the many recreational vessels and sightseeing cruises crammed with selfie-snappers; the FDNY and PDNY 911-style dashing between destinations; and not to forget the non-stop (and I mean non-stop) low-hovering helicopters shuffling the suited CEOs back and forth to their Manhattan meetings.
An engineering team was brought in and their high-tech analysis and testing on how best to combat the volatile condition resulted in steel wave attenuators set on deep draft steel barges as the solution. This combination cushions the marina basin with a gentler undulation by reducing the size and energy of incoming swells and eliminating unnecessary wave movement.
Saved by Steel
One° 15 Brooklyn Marina CEO Estelle Lau tells me, “The marina was initially designed using all Seaflex anchoring but we found that the increased boats and ferries on the waterfront were too powerful for the system. So we built the new attenuators using the same concept as the New York ferry landings, putting piles in to further strengthen the system – doubling the width and tripling the depth of the attenuator.”
Since One° 15 Brooklyn Marina re-opening in May of 2019, the $28 million dollar multi-phase design project has yielded continual praise and positive results; nonetheless, it was met with a series of challenges along the way which were to be expected:
1- Addressing environmental concerns and securing all necessary permits became a lengthy process entailing SBS, Army Corp, Environmental Agency and MTA (Metropolitan Transit Authority) involvement.
2- The position of the R subway train running under the facility required a reduction in piles near the tunnels and prevented the use of anchoring and cables.
3- Taking all precautions, a sophisticated monitoring system had to be installed to avoid the impact area of the tunnels during the pile driving along the attenuator.
4- Disruptions to the summer operations at the marina needed to be minimized.
The engineering crew was resilient in complying with the compulsory rules and restrictions mandated during the course of the daunting infrastructure refurbishment. First, the large concrete blocks initially installed to anchor the docks were repurposed to the inside dock on the marina’s south side. Next, two 185-foot steel barges dubbed as Little Bear One and Little Bear Two, and Polaris the third goliath-in-size 300-footer with a 30-foot beam and 10-foot draft, were secured to the seabed floor, followed by ballasting down the attenuators on piles and driving them into the bay.
One° 15 Brooklyn Marina: a cheerful pier
One° 15 Brooklyn Marina is the place where contemporary meets community! For all your nautical needs, check out its website for more detailed information: https://one15brooklynmarina.com
Article also available in: